- We had some stalls last week. We had to wait for engineers to do calculations in the Wudu area before we could build on the foundations. Then, Lots of workers went down with seasonal viruses and the steel delivery got delayed until this week. However, we are pleased to inform you that we are still running on schedule. This is because the builders had gotten ahead a couple of weeks at the beginning of the project, which has helped to absorb last week’s issues.
- The builders will remain on site over much of the Christmas break, attempting to get back in front.
- We have started looking for carpet quotes and are very close to realizing the interior design.