- We have an updated programme today that keeps us on target to be completed in time for Ramadan InShaAllah. It is a very tight deadline and we pray that there will be no snow!
- Most of the first floor structural steels are now fitted.
- The remaining ground floor steels will continue to be fitted over the next 2 weeks.
- We are ready to order the carpets this week.
- The new Wudu area will be completed by the end of February 2023.
- Also, a tree surgeon is coming next week.