Today’s updates
▪Sisters side first floor is now fitted with roof joists. ▪footings and tree root removal are underway for the main entrance.
▪building parapet is in progress for the fitting of the decorative screen finish.
▪A detailed financial statement has been received from the contractor to account for everything in detail that has been additional to the original contract. There’s some more meetings planned for Br Naz who is currently interrogating it all and he aims to provide some clarity to the fundraising committee shortly InShaAllah

 