2023.06.09 Extension Update

Asalamu alaikum

The sisters block work will be at roof level in a few days.

Roger is doing the lazer cut panel design to get that ordered by next week.

We are going to save money by reducing the spec on the hot water system. I really believe it was over prescribed for our needs.

We are on schedule to complete by third week in August InShaAllah

The potential hold ups are getting the heating and drainage sorted.
Getting the lazer cut panels delivered from Turkey and fitted in time.

The pictures you can see the sisters prayer hall taking shape as well as the residents area on the first floor.
The upstairs brother’s prayer hall looks great after being plastered.

Chris has promised to furnish us with remaining costs with a clear breakdown of all the extras. A few days InShaAllah.